Under this service, the Department of the Interior and Local Government (DILG) submits an endorsement to the DBM for fund release of the LGSF-CMGP. Upon evaluation of the endorsement based on the existing laws, rules and regulations, the Local Government and Regional Coordination Bureau (LGRCB) recommends to the Secretary the release of funds or informs the DILG should a ground for denial be found.
Office or Division
OFFICE OR DIVISION: |
|
CLASSIFICATION: | Highly Technical |
TYPE OF TRANSACTION: | G2G – Government to Government (Between DILG and DBM) |
WHO MAY AVAIL: | Local Government Units (Provinces enumerated under SP No.1 of the FY 2023 General Appropriations Act (GAA), Republic Act (RA) No. 11936 |
Checklist of Requirements
CHECKLIST OF REQUIREMENTS |
TYPE AND NUMBER OF COPY |
WHERE TO SECURE |
Endorsement of DILG Secretary regarding the release of funds for LGSF-CMGP Note: If information is incomplete, incorrect or non-compliant, the DBM shall return the endorsement documents through a letter to the DILG. |
One (1) original copy/scanned copy |
DILG-Office of the Secretary |
Client Steps
Administrative Service-Central Records Division (AS-CRD)
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
1. DILG submits endorsement letter to the AS-CRD. |
1. Receive request. |
None | within 1 hour |
Administrative Assistant (ADAS) I, and Administrative Officer (AO) III and V |
1.1 None |
1.1 Upload all documents to DMS |
None | ||
1.2 Receive the Document Management System (DMS)- generated acknowledgement receipt (AR). |
1.2. Issue DMS-generated AR; and send hardcopy to LGRCB |
None |
Local Government and Regional Coordination Bureau (LGRCB)
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
2.None |
2. Route request to the Division concerned. |
None |
within 2 hours, 50 minutes |
ADAS III/ AO III |
3. None |
3. Evaluate request and prepare action document(s). |
None |
11 working days |
Budget and Management Analyst (BMAN), Budget and Management Specialist (BMS) I, BMS II, Senior BMS |
3.1 None |
3.1.If information is complete, correct and compliant, prepare the following:
|
None |
||
4. None |
4. Review draft action and fund release document(s)in e-Budget, and affix initials on draft fund release documents |
None |
1 working day |
Supervising BMS (SVBMS) |
5. None |
5. Review draft action document(s). Recommend and endorse to Director the draft action/fund release documents (affix initials and/or signature on draft fund release documents) |
None |
1 working day |
Chief BMS (CBMS) |
6. None |
6. Review and recommend approval of action/fund release documents. Tag “For Approval” in e-Budget and sign draft fund release documents |
None |
1 working day |
Director
|
7.None | 7.Send approved fund release documents to the Assistant Secretary for LGRO Group | None | within 4 hours |
AO III/ADAS III |
Office of the Assistant Secretary and Office of the Undersecretary for Local Government and Regional Offices Group (LGRO)
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
8. None |
8. Review draft action/fund release documents and endorse the same to Undersecretary for LGRO Group |
None |
1 working day |
Assistant Secretary |
9. None | 9. Review draft action/fund release documents and endorse the same to Undersecretary for BPE Group | None | Undersectretary |
Office of the Undersecretary for Budget Preparation and Execution (BPE) Group
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
10.None |
10. Review and recommend approval of the action/fund release documents to the DBM Secretary. |
None |
1 working day |
Undersecretary |
Office of the Secretary (OSEC)
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
11. None |
11. Review and approve the action document/s, including signing of the budget release documents. |
None |
3 working days
|
DBM Secretary |
11.1. None |
11.1. Tag “Approve” in the eBudget. |
None |
Executive Assistant (EA)/ Chief-of-Staff |
|
11.2. None | 11.2. Send approved eSARO, eNCA and approved MFS to the BTB-Central Printing and Releasing Unit (CPRU). | None |
EA |
|
12. None | 12. Send printed NCA to OSEC. | None |
ADAS III
BTB-CPRU
|
|
13. None | 13. Sign action documents. | None | DBM Secretary |
Budget Technical Bureau (BTB) - Central Printing and Releasing Unit (CPRU)
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME | PERSON RESPONSIBLE |
14. DILG to access signed Obligational and/or Disbursement Authority/-ies in ADRS | 14. Receive, package and release obligational and disbursement authorities | None | 10 minutes | ADAS III
|
14.1 Download Obligational and/or Disbursement Authority/ies in the ADRS |
14.1 Upload the signed Obligational and/or Disbursement Authority/ies in the ADRS. |
None | ||
14.2 None |
14.2 Tag as "Released" in e-Budget | None | ||
TOTAL | 20 working days | |||
*The processing time may vary depending on the result of evaluation of requests and volume of requests received |