DBM Press Release

DBM Chief explains how government can commit to major projects spanning several years without releasing the entire project cost in one go
 
If a major bridge will cost P10 billion but will take three years to complete, does the government need to put the entire P10 billion in the budget—and release it—all at once?
 
No.
 
Department of Budget and Management (DBM) Secretary Kim Robert C. De Leon explained that while major infrastructure projects may require contractual commitments covering several years, their funding requirements are programmed according to their implementation schedule and remain subject to the annual budget process.
 
In Episode 12 of A.S.K. — Alamin kay Sec. Kim, the Budget Secretary broke down how government plans for big-ticket projects such as bridges, railways, hospitals, and flood control facilities that cannot realistically be completed within a single year.
 
“Ang malalaking proyekto ng gobyerno—tulay, railway, ospital, flood control project—hindi naman parang instant noodles,” Secretary De Leon said.
 
“Hindi puwedeng: ‘Monday, groundbreaking.’ Tapos Friday: ‘Sir, ribbon-cutting na po.’ Sana ganoon kabilis. Pero hindi,” he added.
 
Because these projects undergo several stages and often take years to complete, government must plan not only the total project cost but also the contract period, implementation schedule, and funding requirements for each year.
 
For eligible locally funded multi-year projects, this is where the Multi-Year Contractual Authority (MYCA) comes in.
 
MYCA allows a government agency to enter into a contractual commitment extending beyond one year, subject to applicable DBM rules and requirements.
 
“Kung three years ang trabaho, hindi puwedeng one year lang ang tanaw,” Secretary De Leon stressed.
 
He explained that MYCA enables an eligible multi-year project to be covered by a multi-year contract instead of treating it as though the government’s commitment ends after only one year.
 
This provides greater continuity in project implementation and allows agencies to plan the project through completion.
 
“Hindi puwedeng kalahati na ang tulay, tapos sabihin natin: ‘Okay, hanggang dito muna. Tingnan natin next year kung itutuloy.’ Tulay ang ginagawa natin, Budget Peeps. Hindi cliffhanger,” he said.
 
MULTI-YEAR CONTRACT DOES NOT MEAN ONE-TIME RELEASE
 
Secretary De Leon stressed, however, that having a MYCA does not mean an agency immediately receives the entire cost of the project.
 
Using a P10-billion bridge to be implemented over three years as an example, its funding requirements could be programmed at P3 billion in the first year, P4 billion in the second, and P3 billion in the third.
 
“Ang MYCA ay authority para sa multi-year contractual commitment. Hindi ito isang bagsakang P10-billion check,” he explained.
 
“Iba ang kontrata. Iba rin ang taunang budget. Kaya kahit multi-year ang commitment, annual pa rin ang budget discipline,” he added.
 
Thus, while the contract may cover several years, the project’s annual funding requirements remain subject to the applicable annual appropriations, budgeting, accounting, auditing, and other government safeguards.
 
WHAT ABOUT FOREIGN-ASSISTED PROJECTS?
 
Secretary De Leon also clarified that a different treatment applies to Foreign-Assisted Projects (FAPs) financed through foreign loans.
 
Under applicable rules, foreign loan-funded FAPs do not require MYCA before entering into a multi-year contract because their financing arrangements and governing rules differ from those of locally funded multi-year projects.
 
But the Budget Chief emphasized that this does not mean foreign-assisted projects are exempt from proper planning and budget discipline.
 
Their project scope, financing arrangements, implementation schedules, and annual funding requirements must likewise be clearly established and programmed.
 
“Local man o foreign-assisted, iisa ang expectation: planado ang proyekto mula umpisa hanggang matapos,” Secretary De Leon said.
 
For the Budget Chief, however, multi-year planning ultimately matters not because of the authority or contract itself, but because government projects must translate into actual results for the people.
 
“Para sa Pilipinong tatawid sa tulay, sasakay sa tren, gagamit ng ospital, o makikinabang sa flood control project, hindi naman MYCA ang hinihintay nila. Ang hinihintay nila ay proyekto. Proyektong natapos. Proyektong gumagana. At proyektong talagang napapakinabangan,” he said.
 
Secretary De Leon stressed that when billions of pesos in public funds and several years of implementation are involved, government planning must look beyond the start of a project and toward its completion.
 
“Kapag bilyon-bilyong piso ng taumbayan at ilang taon ng trabaho ang pinag-uusapan, hindi puwedeng hanggang groundbreaking lang ang plano. Dapat hanggang completion. Hanggang resulta. Hanggang sa mamamayan,” he concluded.
 
A.S.K. — Alamin kay Sec. Kim is DBM’s public information series that simplifies the national budget, its processes, and commonly misunderstood concepts so that more Filipinos can understand how public funds are planned and used.
 
Watch A.S.K. Episode 12 — MYCA for Infrastructure and Foreign-Assisted Projects here:
 
 
 
[END]
 
FILIPINO VERSION
 
 
NEWS MATERIAL
Department of Budget and Management
ika-3 ng Oktubre 2026
 
P10-B PROJECT, KAILANGAN BA P10-B DIN AGAD ANG BUDGET? SEC. KIM, IPINALIWANAG KUNG PAANO PINAPLANO NG GOBYERNO ANG MGA MULTI-YEAR PROJECT
DBM Chief, ipinaliwanag kung paano magkaroon ng multi-year commitment para sa malalaking proyekto nang hindi kailangang ilabas agad ang buong project cost
 
Kung nagkakahalaga ng P10 billion ang isang major bridge at tatlong taon itong matatapos, kailangan ba na ilagay na agad sa budget ang buong P10 billion—at ilabas din ito nang sabay-sabay?
 
Hindi.
 
Ipinaliwanag ni Department of Budget and Management (DBM) Secretary Kim Robert C. De Leon na bagama’t maaaring umabot ng ilang taon ang contractual commitments para sa malalaking infrastructure projects, ang funding requirements ng mga ito ay pino-program ayon sa implementation schedule at nananatiling subject sa annual budget process.
 
Sa Episode 12 ng A.S.K. — Alamin kay Sec. Kim, inisa-isa ng Budget Secretary kung paano pinaplano ng gobyerno ang malalaking proyekto gaya ng mga tulay, railway, ospital, at flood control facilities na hindi realistically matatapos sa loob ng isang taon.
 
“Ang malalaking proyekto ng gobyerno—tulay, railway, ospital, flood control project—hindi naman parang instant noodles,” ayon kay Secretary De Leon.
 
“Hindi puwedeng: ‘Monday, groundbreaking.’ Tapos Friday: ‘Sir, ribbon-cutting na po.’ Sana ganoon kabilis. Pero hindi,” dagdag pa niya.
 
Dahil dumadaan sa iba’t ibang stages ang mga ganitong proyekto at kadalasan ay inaabot ng ilang taon bago makumpleto, kailangang planuhin ng gobyerno hindi lang ang total project cost, kundi pati ang contract period, implementation schedule, at funding requirements para sa bawat taon.
 
Para sa mga eligible locally funded multi-year projects, dito pumapasok ang Multi-Year Contractual Authority (MYCA).
 
Pinapayagan ng MYCA ang isang government agency na pumasok sa isang contractual commitment na lalampas sa isang taon, alinsunod sa mga naaangkop na DBM rules at requirements.
 
“Kung three years ang trabaho, hindi puwedeng one year lang ang tanaw,” pagbibigay-diin ni Secretary De Leon.
 
Ipinaliwanag niya na nagbibigay-daan ang MYCA para ang isang eligible multi-year project ay masakop ng isang multi-year contract, sa halip na ituring na parang hanggang isang taon lamang ang commitment ng gobyerno.
 
Nagbibigay ito ng mas maayos na continuity sa implementation ng proyekto at nagbibigay-daan sa mga ahensya na maplano ang proyekto hanggang sa makumpleto ito.
 
“Hindi puwedeng kalahati na ang tulay, tapos sabihin natin: ‘Okay, hanggang dito muna. Tingnan natin next year kung itutuloy.’ Tulay ang ginagawa natin, Budget Peeps. Hindi cliffhanger,” ayon kay Secretary Kim.
 
MULTI-YEAR CONTRACT, HINDI IBIG SABIHIN ONE-TIME RELEASE
 
Binigyang-diin ni Secretary De Leon, gayunman, na ang pagkakaroon ng MYCA ay hindi nangangahulugang matatanggap agad ng isang ahensya ang buong halaga ng proyekto.
 
Halimbawa, kung P10 billion ang halaga ng isang bridge project na ipatutupad sa loob ng tatlong taon, maaaring i-program ang funding requirements nito nang P3 billion sa unang taon, P4 billion sa ikalawang taon, at P3 billion sa ikatlong taon.
 
“Ang MYCA ay authority para sa multi-year contractual commitment. Hindi ito isang bagsakang P10-billion check,” paliwanag niya.
 
“Iba ang kontrata. Iba rin ang taunang budget. Kaya kahit multi-year ang commitment, annual pa rin ang budget discipline,” dagdag pa niya.
 
Ibig sabihin, kahit ilang taon ang saklaw ng kontrata, ang annual funding requirements ng proyekto ay mananatiling saklaw ng applicable annual appropriations, budgeting, accounting, auditing, at iba pang government safeguards.
 
PAANO NAMAN ANG FOREIGN-ASSISTED PROJECTS?
 
Ipinaliwanag din ni Secretary De Leon na iba ang treatment para sa Foreign-Assisted Projects (FAPs) na pinopondohan sa pamamagitan ng foreign loans.
 
Sa ilalim ng applicable rules, hindi kailangan ng MYCA ang foreign loan-funded FAPs bago pumasok sa isang multi-year contract dahil iba ang kanilang financing arrangements at governing rules kumpara sa locally funded multi-year projects.
 
Gayunman, binigyang-diin ng Budget Chief na hindi ibig sabihin nito na exempted ang foreign-assisted projects sa maayos na pagpaplano at budget discipline.
 
Kailangan ding malinaw na naitatakda at napaplano ang project scope, financing arrangements, implementation schedules, at annual funding requirements ng mga ito.
 
“Local man o foreign-assisted, iisa ang expectation: planado ang proyekto mula umpisa hanggang matapos,” ayon kay Secretary De Leon.
 
Para sa Budget Chief, mahalaga ang multi-year planning hindi lamang dahil sa authority o contract, kundi dahil kailangang mauwi sa aktuwal na resulta para sa mga Pilipino ang mga proyekto ng gobyerno.
 
“Para sa Pilipinong tatawid sa tulay, sasakay sa tren, gagamit ng ospital, o makikinabang sa flood control project, hindi naman MYCA ang hinihintay nila. Ang hinihintay nila ay proyekto. Proyektong natapos. Proyektong gumagana. At proyektong talagang napapakinabangan,” aniya.
 
Binigyang-diin ni Secretary De Leon na kapag bilyon-bilyong piso ng public funds at ilang taon ng implementation ang pinag-uusapan, kailangang higit pa sa pagsisimula ng isang proyekto ang saklaw ng government planning—dapat ay hanggang sa makumpleto ito.
 
“Kapag bilyon-bilyong piso ng taumbayan at ilang taon ng trabaho ang pinag-uusapan, hindi puwedeng hanggang groundbreaking lang ang plano. Dapat hanggang completion. Hanggang resulta. Hanggang sa mamamayan,” pagtatapos niya.
 
Ang A.S.K. — Alamin kay Sec. Kim ay serye ng DBM tungkol sa pagbibigay-kaalaman sa publiko na nagpapaliwanag sa national budget, mga proseso nito, at mga konseptong madalas hindi nauunawaan sa simple at madaling maintindihan na paraan—dahil hindi dapat nakalilito ang budget; dapat itong maunawaan ng bawat Pilipino.
 
Panoorin ang A.S.K. Episode 12 — MYCA for Infrastructure and Foreign-Assisted Projects dito:
 
 
 
[END]